1.0 PURPOSE:
To describe a standard operating procedure for replacement of gland packing of pumps and reactors.
2.0 SCOPE:
The standard operating procedure describes in detail the method of replacing gland packing of pumps and reactors in the plant.
3.0 RESPONSIBILITY:
The responsibility of replacing the gland packing of pumps and reactors lies with the staff of rank not lower than junior utility operator of maintenance department.
The responsibility of preparing, reviewing and approving thestandard operating procedure lies with the Manager - Maintenance, Head of Production and Head of QAD respectively.
4.0 METHOD:
4.1 Isolate the equipment electrically.
4.2 Close the suction and discharge valves in case of pumps and drain the liquid.
4.3 Open the gland follower.
4.4 Take out all the old gland ropes with a metallic hook.
4.5 Clean the stuffing box thoroughly with cloth.
4.6 Take a new gland rope of suitable size.
4.7 Cut the gland rope into pieces of required length and insert only one at a time inside the stuffing box with the help of gland follower.
4.8 Ensure that the joints of all packing rings are diametrically opposite.
4.9 Insert required number of rings and tighten the gland follower suitably.
4.10 Open the suction and delivery valves, in case of pumps and restore the power supply to the equipment.
4.11 Start the pump/reactor, if the gland leaks, slowly tighten the gland follower bolts till the leakage is arrested in running condition.