1.0 PURPOSE:
To describe a standard operating procedure for installing the solvent recovery column.
2.0 SCOPE:
The standard operating procedure describes in detail the method of installing the solvent recovery column.
3.0 RESPONSIBILITY:
The responsibility of installing the solvent recovery column lies with the staff of rank not lower than the maintenance engineer.
The responsibility of preparing, reviewing and approving the standard operating procedure lies with the Manager - Maintenance, Head of Production and Head of QAD respectively.
4.0 METHOD:
4.1 Locate the site where the solvent recovery column has to be installed.
4.2 Construct foundation to seat the pedestals of the distillation still.
4.3 Place the distillation still on the foundation.
4.4 Check the level of the still with spirit level.
4.5 Place the sieve tray segment-1 on the distillation still, fix it and check the level.
4.6 Place the sieve tray segment-2 on the segment-1, fix it and check the level.
4.7 Fix the top cover to the sieve tray segment-2.
4.8 Make a platform around the top of first sieve tray segment.
4.9 Place the two condensers on the platform and fix them.
4.10 Fix third condenser, above the previous two condensers.
4.11 Construct foundation for the pumps.
4.12 Place the pumps on the foundation and give electrical connections.
4.13 Construct foundation for reactor structure and fourth condenser.
4.14 Fix the reactor and condenser structures on the foundation.
4.15 Place the reactor and condenser on structure and fix them.
4.16 Make a platform for reactor.
4.17 Give electrical connection to the reactor motor.
4.18 Construct foundation for receivers structure.
4.19 Fix the structures on foundation.
4.20 Place the receivers on structures and fix them.
4.21 Interconnect all the equipments as per the planned layout.
4.22 Give service lines like steam, chilled water and tower water as per the layout.
4.23 Insulate the distillation still, sieve tray column segments and steam lines with mineral wool.
4.24 Arrange digital thermometer in the thermometer pocket provided on the distillation still.
5.0 RECORDING:
The responsibility of recording the installation details in the history card lies with staff of rank not lower than the maintenance engineer.
Solvent recovery column, engineering,