img

PREVENTIVE MAINTENANCE OF VARIOUS EQUIPMENT IN THE PLANT

To describe  a  standard operating procedure for  preventive   maintenance of various equipments.

Sharing is caring, show love and share the thread with your friends.

Description

1.0 PURPOSE:
         
    To describe  a  standard operating procedure for  preventive   maintenance of various equipments.
    
2.0    SCOPE:
    
    The  standard  operating procedure describes  in  detail  the   method of preventive maintenance of various equipments namely   reactors,  centrifuges,  fluid  bed dryer, sifters, blenders, pumps, dryers, pressure filters, leaf filters, microniser, receivers, nutsch filter, chariot, blowers, exhaust fans, DM water plant, soft water plant, water storage tanks, condensers, vacuum pumps, Boiler, Distilled water plant, Dry air system & Air handling system.
    
3.0    RESPONSIBILITY:
    
    The  responsibility  of carrying out  preventive  maintenance  lies with the staff of rank not lower than the supervisor  of  maintenance department.
              
The responsibility of preparing, reviewing  and approving  the  standard  operating  procedure lies with the Manager  -  Maintenance,  Head of Production and Head of QAD respectively.
    
4.0    METHOD:
    
4.1    Philosophy:
    
4.1.1    Preventive maintenance shall be carried out for all utilities and process equipment as per the prescribed schedules and procedures.
    
4.1.2    Preventive maintenance procedures for various equipment and their frequency are in place.
    
4.1.3    Job instruction shall be followed as per format no. xxxxx shown in Annexure-II during preventive maintenance of equipment by the doer and checker.
    
    
    
4.1.4    Job instruction card shall have the unique number for identification.
    
4.1.5    By referring job instruction card unique number a compliance report as per format shall be made and approved by Head of the maintenance department.
    
4.1.6    Preventive maintenance schedule format No. MTxxxxxof various equipment shall be informed to production department to facilitate clearance for the equipment by internal correspondence.
    
4.2    Reactors:
        
4.2.1    Isolate the equipment electrically.                 

4.2.2     Ensure  that the reactor is  thoroughly   cleaned.  

4.2.3    Open  the  bearing  housing covers and apply  grease  to  the  bearings.               

4.2.4      Check the condition of V-belts.  If any cuts are observed  on  the  tread, replace the belts as per SOP REPLACEMENT OF V-BELTS OF REACTORS, VACUUM PUMPS, COMPRESSORS, AIR COMPRESSORS, CENTRIFUGES, BLOWER ETC. Check  the  deflection  of V-belts between the two pulleys.  Replace  the   V-belts if the deflection of the V-belts is more than 1" even after adjusting the Motor base.
    
4.2.5    Check the condition of facewell coupling, coupling bolts and  rubber bushes. If the coupling is cracked / loose on shaft or   with enlarged holes replace the coupling as per SOP REPLACEMENT OF COUPLING BOLTS OF REACTORS.. If the coupling bolts and rubber bushes are damaged /  deformed, replace as per SOP REPLACEMENT OF COUPLING BOLTS OF REACTORS.

4.2.6     Check  the gear box and Motor cooling fans.  Replace the  fan   if it is found broken and / or loose on shaft. Check for  the  oil leakage from gear box and if required rectify as per  the  SOP REPLACEMENT OF OIL SEALS OF GEAR BOXES..  Top up oil if required.

4.2.7    Tighten  the Agitator bolts and nuts.  Replace if found  damaged  or corroded.  Tighten the baffle bolts  and  Thermowell  clamps.


4.2.8     Check the reactor shell for any damage or pitting. In case of  major  damages,  send the  equipment for repair  as  per  SOP   SENDING  OUT  EQUIPMENT  FOR RECTIFICATION TO THE OUTSIDE AGENCY.& replacement  of gland packing of pumps and reactors.. Incase of Glass lined  reactors,  check the glass lining visually.  If any damage is  observed, carry  out  spark testing.  If the damage  is  confirmed   by   spark testing. Carry out the necessary repair job or relining  of the vessel.

4.2.9    Check the valves for leakage and replace if necessary as  per  the SOP REPLACEMENT OF VALVES 
4.2.10    Test  the  jacket hydraulically up to 1.5  times  the  normal    working pressure as per SOP REPLACEMENT OF COUPLING BOLTS OF REACTORS.

4.2.11    Check the stirrer shaft. If the shaft is wornout or got bent, repair/replace the shaft by sending it to outside agency as per SOP REPAIRING/REPLACING THE AGITATOR/SHAFT OF REACTORS..

4.2.12     Check  the thickness of the reactor shell and jacket at  different locations with the help of Thickness tester.

4.2.13     Restore the power supply to the equipment.

4.2.14    Frequency  :  Once in a year. 

4.2.15    Record the readings in Annexure-III.
    
4.3.0    Centrifuges:

4.3.1        Isolate the equipment electrically.

4.3.2        Check all the lubricating points, If required lubricate them.
        
4.3.3        Replace the brake liners as per SOP REPLACEMENT OF  BREAKE  LINERS  OF  CENTRIFUGE.

4.3.5      Check the condition of V-belt. If the deflection is more than  to  inches and/or cuts are found on the tread replace the  V-belts as per SOP REPLACEMENT OF V-BELTS OF REACTORS, VACUUM PUMPS, COMPRESSORS, AIR COMPRESSORS, CENTRIFUGES, BLOWER ETC.

4.3.6        Replace the brake spring with new spring.

4.3.7        Check the foundation bolts and tighten them.

4.3.8        Check  for any abnormal sound and vibration from the  centrifuge and rectify as per SOP BREAKDOWN  RECTIFICATION  OF CENTRIFUGE.

4.3.9        Replace the clutch liners as per SOP BREAKDOWN  RECTIFICATION  OF CENTRIFUGE..

4.3.10       Restore the power supply to the equipment.

4.3.11       Frequency:  Once in three months.

4.3.12    Record the readings in Annexure-VII.

4.4.0        Fluid Bed Dryer:

4.4.1        Isolate the equipment electrically.

4.4.2        Check the condition of the impeller of the blower.

4.4.3        Check  the  steam  trap and pneumatic  cylinders  for  their  operation.

4.4.4        Check  the  condition of the suction  filter.  If  necessary  replace the filter. 

4.4.5     Clean   the calorifier fins with compressed air.

4.4.6       Replace  the product container gasket.

4.4.7        Check  the gauges and replace if any error  is  found.

4.4.8       Restore the power supply to the equipment.

4.4.9       Frequency  :  Once in a year.                 

4.4.10    Record the readings in Annexure-XV.

4.5          Sifter:

4.5.1      Isolate the equipment electrically.

4.5.2        Lubricate all the bearings.

4.5.3        Replace the V-belt as per SOP EQUIPMENT BREAKDOWN  INVESTIGATION.
4.5.4        Restore the power supply to the equipment.

4.5.5        Check the vibration of the sifter and if necessary adjust the   balancing mechanism.

4.5.6        Frequency  :  Once in a year.        

4.5.7    Record the readings in Annexure-XVII.

4.6.0      Blender :

4.6.1       Isolate the equipment electrically.

4.6.2       Lubricate  the pedestal bearings.

4.6.3        Check  the couplings between motor and gear box.  Replace  if  necessary as per SOP REPLACEMENT OF DAMAGED COUPLINGS/PULLEYS OF REACTORS, PUMPS, MOTORS AND GEAR BOXES..

4.6.4      Replace the oil in the gear box.  If any metal particles  are  found in the oil, proceed as per SOP REPLACEMENT OF OIL SEALS OF GEAR BOXES.

4.6.5     Restore the power supply to the equipment.

4.6.6      Frequency :  Once in a year.        

4.6.7    Record the readings in Annexure-XVII.

4.7.0 
    Pumps:
4.7.1      Isolate the equipment electrically.

4.7.2        Close  the suction and delivery valves and drain  the  liquid  from the suction casing.

4.7.3        Check  the gland packing/mechanical seal,  if  necessary  replace/rectify as per SOP replacement  of gland packing of pumps and reactors.or SOP replacement  of spares of mechanical seal unit of pumps..

4.7.4      Check the coupling alignment, if faulty rectify.

4.7.5       Check the base bolts of pump and motor.

4.7.6     Check the lubricant of the shaft, if necessary fill it.     

4.7.7     Restore the power supply to the equipment.

4.7.8    Frequency  :  Once in six months.    

4.7.9    Record the readings in Annexure-XVIII.

4.8.0     Dryer:

4.8.1     Isolate the equipment electrically.

4.8.2     Lubricate  all the bearings. 

4.8.3       Check the V-belt, if damaged change the V-belt as per SOP BREAKDOWN   RECTIFICATION OF TRAY DRYER.
4.8.4        Check  the  steam trap for proper  operation.  If  necessary,  replace it.

4.8.5     Check and if necessary replace the shaft bearings as per  SOP   BREAKDOWN   RECTIFICATION OF TRAY DRYER.
    
4.8.6    Check  the condition of calorifier.  Replace it if  the  fins   are corroded and/or if tubes are leaking.

4.8.7       Paint the interior of the dryer and the trolley.

4.8.8     Check the  condition of the fan.              

4.8.9     Clean the mesh provided in the suction with  compressed air.

4.8.10     Restore the power supply to the equipment.

4.8.11     Frequency  :  Once in a year.        

4.8.12    Record the readings in Annexure-V.

4.9.0     Pressure Filters:

4.9.1      Check  the  SS cladding of the filter. If  the   cladding  is    damaged   send   the   filter  for   repairs   as   per   SOP   SENDING  OUT  EQUIPMENT  FOR RECTIFICATION TO THE OUTSIDE AGENCY.

4.9.2     Test  the   filter hydraulically  upto 1.5 times  the  normal   working  pressure  as per SOP HYDRAULIC   TESTING  OF  THE  REACTOR JACKET.. If the  main  flanges  are leaking send the filter for repairs as  per  SOP   SENDING  OUT  EQUIPMENT  FOR RECTIFICATION TO THE OUTSIDE AGENCY..

4.9.3       Test  the  jacket  hydraulically upto 1.5  times  the  normal   working  pressure as per SOP HYDRAULIC   TESTING  OF  THE  REACTOR JACKET..  If any  leakage  is observed, weld or replace the jacket as per requirement.

4.9.4      Check  the saddle and wheels for any damages and  rectify  if  necessary.

4.9.5       Check the thickness of the shell and jacket.

4.9.6       Frequency:  Once in a year.

4.9.7    Record the readings in Annexure-VIII.

4.10.0     Leaf Filters: 

4.10.1        Check   the SS cladding of leaf filter.  If the  cladding  is  damaged   send  the  filter  for  repair  as  per   SOP   SENDING  OUT  EQUIPMENT  FOR RECTIFICATION TO THE OUTSIDE AGENCY.

4.10.2        Test  the  filter hydraulically  up to 1.5 times  the  normal   working  pressure  as per. HYDRAULIC   TESTING  OF  THE  REACTOR JACKET.  If  the  main   flanges  are leaking send the filter  for repair  as per  SOP. SENDING  OUT  EQUIPMENT  FOR RECTIFICATION TO THE OUTSIDE AGENCY..

4.10.3      Test  the jacket  hydraulically up to 1.5 times  the   normal   working  pressure as per SOP HYDRAULIC   TESTING  OF  THE  REACTOR JACKET..  If any  leakage  is observed, weld or replace the jacket as per requirement.

4.10.4        Check  the saddle and wheels for any damages and  rectify  if  necessary.

4.10.5        Check the thickness of jacket and shell.

4.10.6        Frquency: Once in a year. 

4.10.7    Record the readings in Annexure-IX.

4.11.0     Microniser:

4.11.1       Check  for the leaks of various joints.                       

4.11.2       Check  the condition of inner milling ring. If the holes  are   enlarged replace the ring with new one.

4.11.3       Clean the filters in the air line.              

4.11.4       Frequency  :  Once in a year.        

4.11.5    Record the readings in Annexure-VI.

4.12.0       Receivers:

4.12.1       Check the condition of all the nozzels.

4.12.2       Check the condition of all the valves.

4.12.3       Test  the  receiver hydraulically (1.5 times to  the  working  pressure) as per HYDRAULIC   TESTING  OF  THE  REACTOR JACKET..

4.12.4       Check the thickness of the receiver shell.

4.12.5     Frequency  :  Once in a year.        

4.12.6    Record the readings in Annexure-IV.

4.13.0       Nutsch Filters:

4.13.1       Check the condition of filter plate. 

4.13.2       Check the wheels of the nutsch filter and if necessary change  them.

4.13.3       Check  the condition of main flange cladding.  If it is  damaged send it for repair as per SOP SENDING  OUT  EQUIPMENT  FOR RECTIFICATION TO THE OUTSIDE AGENCY..

4.13.4       Check the gasket condition. If it is damaged  replace it.

4.13.5       Check the thickness of Nutsch filter.

4.13.6     Lubricate the wheels.

4.13.7     Frequency  :  Once in a year.        

4.13.8    Record the readings in Annexure-X.

4.14.0       Chariot:

4.14.1       Check the condition of nipples.

4.14.2       Check the condition of the bottom valve.

4.14.3     Check the condition of the wheels.

4.14.4     Check the thickness of the chariot.

4.14.5     Frequency  :  Once in a year. 

4.14.6    Record the readings in Annexure-XI.

    
4.15.0     Blowers:

4.15.1       Check the bearing condition.

4.15.2       Check the base bolts. 

4.15.3       Lubricate the bearings of motor and blower shaft.

4.15.4       Check the condition of V-Belt.

4.15.5       Frequency  :  Once in a year.        

4.15.6    Record the readings in Annexure-XIV.

4.16.0       Exhaust Fan:

4.16.1     Lubricate the bearings.

4.16.2       Check the fan condition.

4.16.3      Frequency  :  Once in a year.        

4.16.4    Record the readings in Annexure-XIV.

4.17.0     DM Water Plant:

4.17.1      Check  the  condition of rubber lining of pipes and  beds  at  different  places.  If the rubber lining peels off  send  for   repair. 

4.17.2       Wash the resin with water .Make up the resin if required.

4.17.3       Check  the view glasses of Mixed-Bed.If any  cracks  observed  replace the glasses with new one.

4.17.4       Check the condition of diaphragm of valves near injectors. If  damaged, replace the diaphragms. 
    
4.17.5     Clean the injectors and nozzles.

4.17.6       Frequency: Once in a year.

4.17.7    Record the readings in Annexure-XII.

4.18.0         Soft Water Plants:

4.18.1       Wash the resin with water. Make up the resin if required.

4.18.2       Clean the injector and nozzles.

4.18.3     Frequency: Once in a year.

4.18.4    Record the readings in Annexure-XIII.

4.19.0         Water Storage Tanks:

4.19.1       Pump/Drain out water in the storage tank.

4.19.2       Clean the walls and bottom portion of the storage tanks using   wire brush.

4.19.3       After  cleaning with wire brush, clean the walls  with  water  jet.

4.19.4       Pump/Drain the contaminated water from the storage tank.

4.19.5       Repeat the steps 4.18.3 and 4.18.4 for 3 more times.

4.19.6     Frequency: Once in a year.
    
4.20.0    Glass Lined Reactors: 
    
4.20.1    Isolate the equipment electrically.                 

    
4.20.2     Ensure that the reactor is thoroughly cleaned.  

4.20.3    Open the bearing housing covers and apply grease to the bearings of motor.

4.20.4      Check the condition of V-belts.  If any cuts are observed  on  the  tread, replace the belts as per REPLACEMENT OF V-BELTS OF REACTORS, VACUUM PUMPS, COMPRESSORS, AIR COMPRESSORS, CENTRIFUGES, BLOWER ETC.. Check  the  deflection  of V-belts between the two pulleys.  Replace  the   V-belts if the deflection of the V-belts is more than 1" even after adjusting the Motor base.
    
4.20.5    Tighten the bolts of agitator and gear box coupling.
    
4.20.6    Check  the gear box and Motor cooling fans.  Replace the  fan   if it is found broken and / or loose on shaft. Check for  the  oil leakage from gear box and if required rectify as per  the  SOP REPLACEMENT OF OIL SEALS OF GEAR BOXES..  Top up oil if required.
    
4.20.7    Inspect the glass lining visually after thorough cleaning. Carryout the spark test at 5-6 KV only on doubtful spots. If the damage is confirmed by spark testing carry out the necessary repair job or relining of the vessel.
    
4.20.8    Check the valves for leakage and replace if necessary as per the SOP REPLACEMENT OF VALVES.
    
4.20.9    Replace the gaskets of all ports (Nozzles) if they has become hard.
    
4.20.10    Replace the gland packing rings of agitator of the equipment.
    
4.20.11    Replace the gland packing rings of the bottom outlet valve.
    
4.20.12    Replace the Teflon seating of the bottom outlet valve.
    
4.20.13    Test the jacket hydraulically up to 1.5 times the normal working pressure as per SOP HYDRAULIC   TESTING  OF  THE  REACTOR JACKET.
    
4.20.14    Check the thickness of the reactor jacket at different locations with the help of thickness tester.
    
4.20.15    De-scale the jacket using sodium hypochlorite solution.
    
4.20.16    Restore the power supply to the equipment.
    
4.20.17    Frequency: Once in three months.
    
4.21.0    Condensers:
    
4.21.1    Clean the glass condenser coil with diluted HCl (10%).
    
4.21.2    SS316 condensers.
    
4.21.2.1    Clean the condenser tubes using wire brush.
    
4.21.2.2    Test the condenser tubes hydraulically up to 1.5 times the normal working pressure as per SOP HYDRAULIC   TESTING  OF  THE  REACTOR JACKET.
    
4.21.2.3    Check all the nozzles for their intactness.
    
4.21.2.4    Record the readings in Annexure-XIX.
    
4.22.0    Vacuum pumps:
    
4.22.1    Isolate the equipment electrically.
    
4.22.2    Close the vacuum valve and water valve.
    
4.22.3    Remove the pump from foundation frame.
    
4.22.4    Dismantle the pump.
    
4.22.5    Check the bearing condition. If worn out replace with new.
    
4.22.6    Check the control discs condition. If found worn out rectify the problem by machining.
    
4.22.7    Check the couplings condition. If found damaged replace them.
    
4.22.8    Check the gland packing. If necessary replace them.
    
4.22.9    Check the foundation bolts.
    
4.22.10    Assemble the pump and apply lubricant to the bearings.
    
4.22.11    Check the alignment.
    
4.22.12    Restore the power supply to the equipment.
    
4.22.13    Record the reading in Annexure-XX.
    
4.23.0    Boiler
    
4.23.1    Isolate the boiler electrically.
    
4.23.2    Clean the tubes with wire brush.
    
4.23.3    Descale the boiler with Sulphamic Acid.
    
4.23.4    Check the condition of safety valves.
    
4.23.5    Check the condition of the mobery switch.
    
4.23.6    Check boiler feed water pump and motor alignment.
    
4.23.7    Check the blower condition.
    
4.23.8    Check the bearing condition of blower, and motor.
    
4.23.9    Check the furnace brick lining.
    
4.23.10    Check the fire grate condition.
    
4.23.11    Check the gauge glasses condition.
    
4.23.21    Record the reading in Annexure-XXI
    
    
4.24.0    Distilled water plant
    
4.24.1    Check the steam valve condition.
    
4.24.2    Descale the distilled water plant and condenser tubes.
    
4.24.3    Descale the condenser shell.
    
4.24.4    Record the readings in Annexure-XXII
    
4.25.0    Dry air system
    
4.25.1    Check the pre filters and end filters condition and clean them.
    
4.25.2    Check the Activated Aluminia condition. If necessary, replace with new.
    
4.25.3    Check the Pneumatic control valves.
    
4.25.4    Check the Air purging time and quantity of purge.
    
4.25.5    Check the Non-return valves condition.
    
4.25.6    Record the reading in Annexure-XXIII.
    
4.26.0    Air handing system
    
    Preventive maintenance shall be carried out as per SOP PREVENTIVE MAINTENANCE OF AIR HANDLING SYSTEMS AND AIR EXHAUST SYSTEMS, and record the readings in Annexure-XXIV.
    
5.0          RECORDING:
    
    The responsibility of recording the preventive maintenance in the compliance report lies with the staff of rank not lower than the maintenance engineer.

    

Tags

Various equipment in the plant, engineering

References

View / Download