1.0  PURPOSE:
    
    To describe  a  standard operating procedure for   installation  of sampling booth.
    
2.0    SCOPE:
    
     The  Standard opering procedure describes in detail the  method  of installation of sampling booth.
    
3.0    RESPONSIBILITY:
    
    The  responsibility  of carrying out installation  of  sampling   booth  as  per the standard operating procedure lies  with  the   staff of rank not lower than Maintenance Engineer.
        
The  responsibility of preparing, reviewing  and approving  the   standard  operating  procedure lies with the  Manager  -  Maintenance, Head of Production and Head of QAD respectively.
    
4.0    METHOD:
    
4.1      Assemble  the unit in position and clean.

4.2        Fix the manometer, fill it with manometer liquid till the scale  to be adjusted to zero.

4.3        Give electrical connections to the blower motor and tube light.

4.4        Give  earth connections to the unit to  a suitable earth  plate  as per Indian Standard Act.

4.5        Switch on the unit and run contineously for half and hour.    

4.6        Check the unit for noticeable noise or vibration.             


5.0        RECORDING:

    The responsibility of recording of installation  details in the   history  card lies with the staff of rank  not lower  than  the  chargeman.