1.0 OBJECTIVE
1.1 To lay down the procedure for operation of water bath, (NEOLAB).
Equipment identification No: xxxxx
2.0 SCOPE
2.1 This SOP covers the operation procedure of Water bath
3.0 RESPONSIBILITY
3.1 Microbiologist
3.0 ACCOUNTABILITY
4.1 Head - Quality Control
5.0 PROCEDURE
5.1 Connect the instrument to electrical socket for power supply ad put on the switch to start up.
5.2 Check that the heating coil should be properly merged under water.
5.3 Put ON the instrument by switch provided on the instrument as POWER.
5.4 Rotate the multi turn knob clockwise to SET the required temperature. The temperature displays in the monitor.
5.5 Press the RED SET button to read the set temperature.
5.6 After use, put OFF the instrument POWER switch and main supply.
END OF DOCUMENT