1.0 PURPOSE:
To describe a standard operating procedure for replacement of damaged couplings/pulleys of reactors, pumps, motors and gear boxes.
2.0 SCOPE:
The standard operating procedure describes in detail the method of replacing damaged couplings/pulleys of reactors, pumps, motors and gear boxes in the plant.
3.0 RESPONSIBILITY:
The responsibility of replacing the couplings/pulleys of reactors, pumps, motors and gear boxes lies with the staff of rank not lower than junior utility operator of maintenance department.
The responsibility of preparing, reviewing and approving the standard operating procedure lies with the Manager - Maintenance, Head of Production and Head of QAD respectively.
4.0 METHOD:
4.1 Isolate the equipment electrically.
4.2 Remove the coupling / pulleys guard.
4.3 Decouple motor and drive unit.
4.4 Remove the locking bolt of coupling / pulley.
4.5 Remove the coupling / pulley using puller.
4.6 Fix the new coupling / pulley with key.
4.7 Lock the coupling / pulley with lock nut or bolt.
4.8 Incase of pumps assemble the motor and pump, keeping the star washer between the couplings of motor and pump. Incase of reactor insert the bush bolts to the coupling and tighten the bolts.
4.9 Align the coupling / pulleys.
4.10 Fix the coupling / pulleys guard.
4.11 Restore the power supply to the equipment.
Damaged couplings, reactors pumps, motors ,gear boxes